In a highly available (e.g., >99.9%) virtual environment, which of the following times would be the MOST appropriate to perform failover testing?

The correct answer is D. During a scheduled maintenance window. See the full explanation below for the reasoning.

Question

In a highly available (e.g., >99.9%) virtual environment, which of the following times would be the MOST appropriate to perform failover testing?

Options

  • ABetween midnight on Friday and midnight on Sunday
  • BAfter business hours
  • CDuring off-peak times
  • DDuring a scheduled maintenance window

How the community answered

(50 responses)
  • A
    8% (4)
  • B
    16% (8)
  • C
    4% (2)
  • D
    72% (36)