Implementing a process in a change management system takes place after:
The correct answer is D. approval by the CAB. See the full explanation below for the reasoning.
Question
Implementing a process in a change management system takes place after:
Options
- Arigorous peer review.
- Bconsultation with the vendor.
- Cinitial test in a sandbox.
- Dapproval by the CAB.
How the community answered
(33 responses)- A3% (1)
- B6% (2)
- C12% (4)
- D79% (26)