A company is migrating their physical servers to virtual. The administrator is tasked with migrating three servers: One application server with a dual-core 3.2GHz processor that reaches 50% CPU…

The correct answer is C. 3,300 MHz for the application server and 5,250 MHz for each web server. See the full explanation below for the reasoning.

Question

A company is migrating their physical servers to virtual. The administrator is tasked with migrating three servers:

One application server with a dual-core 3.2GHz processor that reaches 50% CPU utilization at peak time. Two web servers, each with a dual-core 3.2GHz processor, both reaching 70% CPU utilization at peak time. Currently, the administrator only has two hosts available, so resources will need to be set for the new VMs. Each host has two 2.4GHz quad-core processors. One host is already near maximum capacity, and the second host is at 30% CPU utilization. Which of the following would be the BEST minimum CPU resources set on the second host for the new VMs?

Options

  • A1,600 MHz for the application server and 2,300 MHz for each web server.
  • B3,300 MHz for the application server and 4,600 MHz for each web server.
  • C3,300 MHz for the application server and 5,250 MHz for each web server.
  • D5,250 MHz for the application server and 7,080 MHZ for each web server.

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    15% (3)
  • C
    70% (14)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.

Full CV0-001 Practice