IBM
CUR-051 · Question #46
An analyst is creating a timeline chart showing key events in the correct sequence. Above one of the events, the time bar looks like this: What does the black triangle indicate?
The correct answer is D. There is a controlling item on the chart with a date and time. See the full explanation below for the reasoning.
Question
An analyst is creating a timeline chart showing key events in the correct sequence. Above one of the events, the time bar looks like this:
What does the black triangle indicate?
Options
- AThere is an ordered item on the chart with a date only.
- BThere is a controlling item on the chart with a date only.
- CThere is an ordered item on the chart with a date and time.
- DThere is a controlling item on the chart with a date and time.
How the community answered
(36 responses)- A3% (1)
- B6% (2)
- C14% (5)
- D78% (28)
Community Discussion
No community discussion yet for this question.