An analyst is creating a timeline chart showing key events in the correct sequence. Above one of the events, the time bar looks like this: What does the black triangle indicate?

The correct answer is D. There is a controlling item on the chart with a date and time. See the full explanation below for the reasoning.

Question

An analyst is creating a timeline chart showing key events in the correct sequence. Above one of the events, the time bar looks like this:

What does the black triangle indicate?

Options

  • AThere is an ordered item on the chart with a date only.
  • BThere is a controlling item on the chart with a date only.
  • CThere is an ordered item on the chart with a date and time.
  • DThere is a controlling item on the chart with a date and time.

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    14% (5)
  • D
    78% (28)