Avixa
CTS · Question #95
The installation of a complex AV project is planned to be completed within 6 months. What is the MOST cost-effective plan for ordering the equipment for the project?
The correct answer is D. Order equipment to be delivered on a "just in time" basis according to the installation schedule. See the full explanation below for the reasoning.
AV Installation
Question
The installation of a complex AV project is planned to be completed within 6 months. What is the MOST cost-effective plan for ordering the equipment for the project?
Options
- AOrder everything as soon as the contract is signed.
- BPlace the order 5 days before the scheduled day for starting installation.
- COrder each piece of equipment to be delivered as soon as possible.
- DOrder equipment to be delivered on a "just in time" basis according to the installation schedule.
How the community answered
(28 responses)- A11% (3)
- B4% (1)
- C7% (2)
- D79% (22)
Topics
#procurement#just-in-time#project management#installation scheduling
Community Discussion
No community discussion yet for this question.