nerdexam
Avixa

CTS · Question #95

The installation of a complex AV project is planned to be completed within 6 months. What is the MOST cost-effective plan for ordering the equipment for the project?

The correct answer is D. Order equipment to be delivered on a "just in time" basis according to the installation schedule. See the full explanation below for the reasoning.

AV Installation

Question

The installation of a complex AV project is planned to be completed within 6 months. What is the MOST cost-effective plan for ordering the equipment for the project?

Options

  • AOrder everything as soon as the contract is signed.
  • BPlace the order 5 days before the scheduled day for starting installation.
  • COrder each piece of equipment to be delivered as soon as possible.
  • DOrder equipment to be delivered on a "just in time" basis according to the installation schedule.

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    7% (2)
  • D
    79% (22)

Topics

#procurement#just-in-time#project management#installation scheduling

Community Discussion

No community discussion yet for this question.

Full CTS Practice