Question

The installation of a complex AV project is planned to be completed within 6 months. What is the MOST cost-effective plan for ordering the equipment for the project?

Options

  • AOrder everything as soon as the contract is signed.
  • BPlace the order 5 days before the scheduled day for starting installation.
  • COrder each piece of equipment to be delivered as soon as possible.
  • DOrder equipment to be delivered on a "just in time" basis according to the installation schedule.