nerdexam
Avixa

CTS · Question #83

Milestones are key events or deliverables in a project. On a Gantt Chart or Network Diagram, milestones are represented by a(n)

The correct answer is B. diamond or triangle.. See the full explanation below for the reasoning.

Question

Milestones are key events or deliverables in a project. On a Gantt Chart or Network Diagram, milestones are represented by a(n)

Options

  • Acircle or oval.
  • Bdiamond or triangle.
  • Csquare or rectangle.
  • Dasterisk or apostrophe.

How the community answered

(43 responses)
  • A
    14% (6)
  • B
    72% (31)
  • C
    5% (2)
  • D
    9% (4)

Community Discussion

No community discussion yet for this question.

Full CTS Practice