Milestones are key events or deliverables in a project. On a Gantt Chart or Network Diagram, milestones are represented by a(n)

The correct answer is B. diamond or triangle. See the full explanation below for the reasoning.

AV Installation

Question

Milestones are key events or deliverables in a project. On a Gantt Chart or Network Diagram, milestones are represented by a(n)

Options

  • Acircle or oval.
  • Bdiamond or triangle.
  • Csquare or rectangle.
  • Dasterisk or apostrophe.

How the community answered

(43 responses)
  • A
    14% (6)
  • B
    72% (31)
  • C
    5% (2)
  • D
    9% (4)

Topics

#project management#Gantt chart#milestones#network diagram