nerdexam
Avixa

CTS · Question #42

After there is an approved labor change to a project, what should the project manager do NEXT?

The correct answer is A. update the schedule. See the full explanation below for the reasoning.

AV Installation

Question

After there is an approved labor change to a project, what should the project manager do NEXT?

Options

  • Aupdate the schedule
  • Border the equipment
  • Cissue an invoice for the change
  • Dinform the purchasing department

How the community answered

(40 responses)
  • A
    83% (33)
  • B
    10% (4)
  • C
    3% (1)
  • D
    5% (2)

Topics

#project management#change order#schedule management#labor planning

Community Discussion

No community discussion yet for this question.

Full CTS Practice