After there is an approved labor change to a project, what should the project manager do NEXT?
The correct answer is A. update the schedule. See the full explanation below for the reasoning.
AV Installation
Question
After there is an approved labor change to a project, what should the project manager do NEXT?
Options
- Aupdate the schedule
- Border the equipment
- Cissue an invoice for the change
- Dinform the purchasing department
How the community answered
(40 responses)- A83% (33)
- B10% (4)
- C3% (1)
- D5% (2)
Topics
#project management#change order#schedule management#labor planning