Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the AV Project Manager should have scheduled is
The correct answer is B. testing and verification. See the full explanation below for the reasoning.
Performance, Maintenance, and Repair
Question
Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the AV Project Manager should have scheduled is
Options
- Atraining the client.
- Btesting and verification.
- Cinvoicing and project close out.
- Dpreventative maintenance schedule.
How the community answered
(26 responses)- A8% (2)
- B77% (20)
- C12% (3)
- D4% (1)
Topics
#project lifecycle#testing and verification#commissioning#project management
Community Discussion
No community discussion yet for this question.