What is the document that shows project tasks, indicating their allocated time, dependencies, and relationships between activities?

The correct answer is B. Gantt chart. See the full explanation below for the reasoning.

AV Installation

Question

What is the document that shows project tasks, indicating their allocated time, dependencies, and relationships between activities?

Options

  • Aflow chart
  • BGantt chart
  • Cneeds analysis
  • DVenn diagram

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    80% (33)
  • C
    12% (5)
  • D
    2% (1)

Topics

#Gantt chart#project scheduling#task dependencies#project management