Avixa
CTS · Question #23
What is the document that shows project tasks, indicating their allocated time, dependencies, and relationships between activities?
The correct answer is B. Gantt chart. See the full explanation below for the reasoning.
AV Installation
Question
What is the document that shows project tasks, indicating their allocated time, dependencies, and relationships between activities?
Options
- Aflow chart
- BGantt chart
- Cneeds analysis
- DVenn diagram
How the community answered
(41 responses)- A5% (2)
- B80% (33)
- C12% (5)
- D2% (1)
Topics
#Gantt chart#project scheduling#task dependencies#project management