CTS · Question #229

According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?

The correct answer is D. Milestone X. See the full explanation below for the reasoning.

Audiovisual Design

Question

According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?

Exhibit

CTS question #229 exhibit

Options

  • AWeek 3
  • BWeek 4
  • CActivity B
  • DMilestone X

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    15% (6)
  • C
    3% (1)
  • D
    75% (30)

Topics

#Gantt chart#project scheduling#milestones#project management