According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?
The correct answer is D. Milestone X. See the full explanation below for the reasoning.
Audiovisual Design
Question
According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?
Exhibit
Options
- AWeek 3
- BWeek 4
- CActivity B
- DMilestone X
How the community answered
(40 responses)- A8% (3)
- B15% (6)
- C3% (1)
- D75% (30)