In order to estimate project task duration, one needs to understand the effort required to complete the expected scope and:

The correct answer is D. Resource availability. See the full explanation below for the reasoning.

AV Installation

Question

In order to estimate project task duration, one needs to understand the effort required to complete the expected scope and:

Options

  • AClient budget
  • BUser experience
  • CRequired training
  • DResource availability

How the community answered

(61 responses)
  • A
    13% (8)
  • B
    7% (4)
  • C
    5% (3)
  • D
    75% (46)

Topics

#project scheduling#task duration#resource availability#scope estimation

Community Discussion

No community discussion yet for this question.