On a construction project awarded through a competitive process, the electrical contractor says that the AV company is responsible for the installation of conduit. What project document(s) would…

The correct answer is D. bid (tender) documents. See the full explanation below for the reasoning.

AV Installation

Question

On a construction project awarded through a competitive process, the electrical contractor says that the AV company is responsible for the installation of conduit. What project document(s) would determine responsibility?

Options

  • Aestimate
  • Bsubmittals
  • Cproposal cover letter
  • Dbid (tender) documents

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    9% (2)
  • D
    83% (19)

Topics

#bid documents#scope of work#construction contracts#conduit responsibility