nerdexam
Avixa

CTS · Question #197

A change order (variation) is best defined as a:

The correct answer is D. Change to the scope of an awarded project. See the full explanation below for the reasoning.

Audiovisual Design

Question

A change order (variation) is best defined as a:

Options

  • AChange to the technician's salary
  • BPrice change to a vendor purchase order
  • CDrawing change to document CAD details
  • DChange to the scope of an awarded project

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    14% (4)
  • C
    3% (1)
  • D
    76% (22)

Topics

#change order#scope management#project documentation

Community Discussion

No community discussion yet for this question.