CTS · Question #164

Which requirement supersedes others when planning an AV project for a client?

The correct answer is D. Local safety ordinances and building codes. See the full explanation below for the reasoning.

AV Installation

Question

Which requirement supersedes others when planning an AV project for a client?

Options

  • AInstitutional policies
  • BExisting infrastructure
  • COrganizational standards
  • DLocal safety ordinances and building codes

How the community answered

(60 responses)
  • A
    5% (3)
  • B
    10% (6)
  • C
    3% (2)
  • D
    82% (49)

Topics

#building codes#safety ordinances#project planning#compliance