CTFL_UK · Question #167
Which of the following has the typical formal review activities in the correct sequence?
The correct answer is C. Planning, kick-off, individual preparation, review meeting. The correct sequence is: planning, kick-off, individual preparation, review meeting, re- work,follow-up. All of the other options have either the activities in the wrong order or activities missing from the strict flow.
Static Testing
Question
Which of the following has the typical formal review activities in the correct sequence?
Options
- AKick-off, review meeting, planning, follow-up.
- BKick-off, planning, review meeting, re-work.
- CPlanning, kick-off, individual preparation, review meeting.
- DPlanning, individual preparation, follow-up, re-work.
How the community answered
(46 responses)- A2% (1)
- B4% (2)
- C83% (38)
- D11% (5)
Explanation
The correct sequence is: planning, kick-off, individual preparation, review meeting, re- work,follow-up. All of the other options have either the activities in the wrong order or activities missing from the strict flow.
Topics
#formal review#review process#review activities sequence