Consider an estimation session where a six-member Agile team (Memb1, ... , Memb6) is performing a planning poker session to estimate a user story (in story points). Team members are using a set of…

The correct answer is D. Memb4 and Memb6, which have produced the most pessimistic and the most optimistic. In Agile estimation sessions, particularly during Planning Poker, the goal is to reach a consensus on the effort required for a user story. The process encourages discussion and collaboration among team members to understand the story's requirements and complexities fully. Exam…

Testing in Software Development Lifecycles

Question

Consider an estimation session where a six-member Agile team (Memb1, ... , Memb6) is performing a planning poker session to estimate a user story (in story points). Team members are using a set of cards with the following values: 1, 2, 3, 5, 8, 13, 21. Below is the outcome produced by the first round of estimation for this session:

Which of the following answers best describes how the estimation session should proceed?

Options

  • AThe final estimate of the user story in story points is determined as the arithmetic mean of all
  • BThe final estimation of the user story in story points is determined as the most frequent
  • CThe final estimate of the user story in story points is determined as the arithmetic mean of the
  • DMemb4 and Memb6, which have produced the most pessimistic and the most optimistic

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    9% (3)
  • D
    83% (29)

Explanation

In Agile estimation sessions, particularly during Planning Poker, the goal is to reach a consensus on the effort required for a user story. The process encourages discussion and collaboration among team members to understand the story's requirements and complexities fully. Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially Cisco, Microsoft, CompTIA, Citrix, EMC, HP, Oracle, VMware, Juniper, Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.

Topics

#planning poker#agile estimation#story points#estimation process