ISTQB
CTFL_001 · Question #41
In general which part of the testing activity is most difficult to estimate? 1 credit
The correct answer is B. Test execution. See the full explanation below for the reasoning.
Question
In general which part of the testing activity is most difficult to estimate? 1 credit
Options
- ATest planning
- BTest execution
- CTest management
- DTest design
How the community answered
(30 responses)- A3% (1)
- B80% (24)
- C7% (2)
- D10% (3)
Community Discussion
No community discussion yet for this question.