Refer to the exhibit. The following test cases need to be run, but time is limited, and it is possible that not all will be completed before the end of the test window The first activity is to run…

The correct answer is C. c, a, d, b, e, g, i, h, f. See the full explanation below for the reasoning.

Question

Refer to the exhibit. The following test cases need to be run, but time is limited, and it is possible that not all will be completed before the end of the test window The first activity is to run any re-tests, followed by the regression test script. Users have supplied their priority order to tests. Which of the following gives an appropriate test execution schedule, taking account of the prioritisation and other constraints?

Exhibit

CTFL_001 question #242 exhibit

Options

  • Ab, c, g, d, e, i, a, f, h
  • Ba, c, d, b, g, e, i, f, h
  • Cc, a, d, b, e, g, i, h, f
  • Dd, c, a, e, b, g, i, f, h

How the community answered

(22 responses)