ISTQB
CTFL_001 · Question #24
Which of the following is a project risk mitigation step you might take as test manager? 1 credit
Sign in or unlock CTFL_001 to reveal the answer and full explanation for question #24. The question stem and answer options stay visible for context.
Test Management
Question
Which of the following is a project risk mitigation step you might take as test manager? 1 credit
Options
- ATesting for performance problems
- BHiring a contractor after a test analyst leaves the company
- CArranging a back-up test environment in case the existing one fails during testing
- DPerforming a project retrospective meeting using the test results after each increment
Unlock CTFL_001 to see the answer
You've previewed enough free CTFL_001 questions. Unlock CTFL_001 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#risk mitigation#project risk#test environment#contingency planning