Which of the following is not decided in the test-planning phase..?
The correct answer is D. Types of test cases. See the full explanation below for the reasoning.
Question
Which of the following is not decided in the test-planning phase..?
Options
- ASchedules and deliverables
- BHardware and software
- CEntry and exit criteria
- DTypes of test cases
How the community answered
(40 responses)- A5% (2)
- B10% (4)
- C3% (1)
- D83% (33)