Testing should be stopped when:

The correct answer is E. It depends on the risks forthe system being tested. See the full explanation below for the reasoning.

Question

Testing should be stopped when:

Options

  • AAll the planned tests have been run
  • BTime has run out
  • CAll faults have been fixed correctly
  • DBoth Aand C
  • EIt depends on the risks forthe system being tested

How the community answered

(50 responses)
  • A
    2% (1)
  • B
    14% (7)
  • C
    6% (3)
  • D
    2% (1)
  • E
    76% (38)