CTFL18 · Question #584
Which of the following would NOT typically be covered in a test summary report?
The correct answer is C. Whether there is any economic benefit in continuing testing beyond the planned date. See the full explanation below for the reasoning.
Question
Which of the following would NOT typically be covered in a test summary report?
Options
- AThe risks associated with unresolved defects found during testing.
- BAny features of the system that were not tested along with reasons.
- CWhether there is any economic benefit in continuing testing beyond the planned date.
- DAn analysis of lessons learned to determine changes for future projects.
How the community answered
(18 responses)- A17% (3)
- B6% (1)
- C72% (13)
- D6% (1)
Community Discussion