CTFL18 · Question #561

In which development life cycle model is regression testing an increasingly important activity as the project progresses?

The correct answer is C. Scrum. See the full explanation below for the reasoning.

Question

In which development life cycle model is regression testing an increasingly important activity as the project progresses?

Options

  • AV-model.
  • BWaterfall.
  • CScrum.
  • DProgressive.

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    81% (34)
  • D
    12% (5)