CTFL18 · Question #540
Which of the following is NOT a test control activity?
The correct answer is D. Set an entry criterion requiring fixes to be retested by a developer before accepting them. See the full explanation below for the reasoning.
Question
Which of the following is NOT a test control activity?
Options
- ARe-prioritize tests because of time pressure
- BChange the test schedule due to viability of a test environment
- CWriting test suspension and resumption criteria in the test plan
- DSet an entry criterion requiring fixes to be retested by a developer before accepting them
How the community answered
(66 responses)- A3% (2)
- B15% (10)
- C9% (6)
- D73% (48)