ISTQB
CTFL18 · Question #431
Which of the following is a project risk?
The correct answer is D. Resource availability. See the full explanation below for the reasoning.
Question
Which of the following is a project risk?
Options
- AInterface complexity
- BData integrity
- CPerformance
- DResource availability
How the community answered
(52 responses)- A4% (2)
- B15% (8)
- C6% (3)
- D75% (39)
Community Discussion