nerdexam
ISTQB

CTFL18 · Question #417

A Test Manager conducts risk assessment for a project. One of the identified risks is: "The sub- contractor may fail to meet his commitment". If this risk materialized, it will lead to delay in…

The correct answer is A. It is a project risk since successful completion of the project depends on successful and timely. See the full explanation below for the reasoning.

Question

A Test Manager conducts risk assessment for a project. One of the identified risks is: "The sub- contractor may fail to meet his commitment". If this risk materialized, it will lead to delay in completion of testing required for the current cycle. Which of the following sentences correctly describes the risk?

Options

  • AIt is a project risk since successful completion of the project depends on successful and timely
  • BIt is a product risk since any risk associated with development timelines is a product risk.
  • CIt is a product risk since default on part of the sub-contractor may lead to delay in release of the
  • DIt is no longer a risk for the Test Manager since an independent party (the sub-contractor) is now

How the community answered

(17 responses)
  • A
    82% (14)
  • B
    12% (2)
  • D
    6% (1)

Community Discussion

No community discussion yet for this question.

Full CTFL18 Practice