Which of the following metrics are useful for monitoring the test progress?
The correct answer is A. The number of features implemented in the code. See the full explanation below for the reasoning.
Question
Which of the following metrics are useful for monitoring the test progress?
Options
- AThe number of features implemented in the code
- BThe number of changes done to the product's requirements
- CPercentage of work done on the user's manuals
- DPercentage of work done in test environment preparation
How the community answered
(27 responses)- A70% (19)
- B4% (1)
- C7% (2)
- D19% (5)