Which of the following statements about estimation of the test effort is WRONG?

The correct answer is D. Effort estimate depends on the budget of the project. See the full explanation below for the reasoning.

Question

Which of the following statements about estimation of the test effort is WRONG?

Options

  • AEffort estimate can be inaccurate because the quality of the product under tests is not known.
  • BOnce the test effort is estimated, resources can be identified and a schedule can be drawn up.
  • CExperience based estimation is one of the estimation techniques.
  • DEffort estimate depends on the budget of the project.

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    3% (1)
  • D
    83% (25)