CTFL18 · Question #313
Which of the following would NOT be a common metric used for monitoring test preparation and execution?
The correct answer is B. Percentage of planned test cases designed. See the full explanation below for the reasoning.
Question
Which of the following would NOT be a common metric used for monitoring test preparation and execution?
Options
- ANumber of Test cases passed and failed
- BPercentage of planned test cases designed
- CNumber of test plan review comments
- DPercentage of tasks complete in test environment preparation
How the community answered
(27 responses)- A15% (4)
- B70% (19)
- C11% (3)
- D4% (1)