What is the Risk Priority Number for risk item number 2? 2 credits

The correct answer is D. 63. See the full explanation below for the reasoning.

Question

What is the Risk Priority Number for risk item number 2? 2 credits

Options

  • A16
  • B2
  • C1
  • D63

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    7% (2)
  • D
    79% (23)