What is the main reason for using a pilot project to introduce a testing tool into an organization?
The correct answer is C. To assess whether the tool will be cost- effective. See the full explanation below for the reasoning.
Question
What is the main reason for using a pilot project to introduce a testing tool into an organization?
Options
- ATo identify the requirements for using a tool
- BTo make a selection between alternative tools
- CTo assess whether the tool will be cost- effective
- DTo ensure the tools fits existing processes without change
How the community answered
(18 responses)- A11% (2)
- C83% (15)
- D6% (1)