CTFL18 · Question #111

Hand over of Testware is a part of which Phase:

The correct answer is C. Test Closure Activities. See the full explanation below for the reasoning.

Question

Hand over of Testware is a part of which Phase:

Options

  • ATest Analysis and Design
  • BTest Planning and control
  • CTest Closure Activities
  • DEvaluating exit criteria and reporting

How the community answered

(32 responses)
  • A
    13% (4)
  • B
    6% (2)
  • C
    78% (25)
  • D
    3% (1)