If capital is to be rationed for only the current period, a firm should probably first consider selecting projects by descending order of .

The correct answer is D. Profitability index. See the full explanation below for the reasoning.

Investment Management

Question

If capital is to be rationed for only the current period, a firm should probably first consider selecting projects by descending order of .

Options

  • ANet present value
  • BPayback period
  • CInternal rate of return
  • DProfitability index

How the community answered

(22 responses)
  • A
    9% (2)
  • B
    5% (1)
  • C
    9% (2)
  • D
    77% (17)