CTAL-TA_SYLL2019 · Question #7

Consider the following requirement: The system shall allow cash advances of at least 200 Euros for all supported credit cards The following credit cards are supported- American Express, Diners…

The correct answer is D. The risk impact for requirement R1 should be categorized as high or very high. The risk impact is the measure of the potential negative consequences of a risk item on the project objectives. It depends on the severity of the defect, the frequency of occurrence, and the visibility to the stakeholders. Since requirement R1 is business critical, any failure…

Test Strategies for AI-based Systems

Question

Consider the following requirement: The system shall allow cash advances of at least 200 Euros for all supported credit cards The following credit cards are supported- American Express, Diners, VISA, Mastercard and Eurocard. The requirement has been identified as business critical. The following test conditions have been derived: 1. The system shall allow cash advances of at least 200 Euros 2. It shall support American Express, Diners, VISA, Mastercard and Eurocard. Assume you are following a risk-based testing strategy, where likelihood and impact are both assessed on a five-point scale ranging from very low to very high The requirement R1 was identified as a risk item during the quality risk analysis process. In total 20 risk items were identified during this process Assume that technical project stakeholders have assessed the likelihood of the requirement R1 risk item at a medium level Given only the information above, which of the following statements is true?

Options

  • AThe test cases associated with requirement R1 shall be run first in the test execution period
  • BThe test cases associated with requirement R1 must be run towards the middle of the test
  • CA large number of test cases should be designed for requirement R1, based on impact
  • DThe risk impact for requirement R1 should be categorized as high or very high

How the community answered

(32 responses)
  • A
    16% (5)
  • B
    3% (1)
  • C
    6% (2)
  • D
    75% (24)

Explanation

The risk impact is the measure of the potential negative consequences of a risk item on the project objectives. It depends on the severity of the defect, the frequency of occurrence, and the visibility to the stakeholders. Since requirement R1 is business critical, any failure in meeting this requirement would have a significant impact on the customer satisfaction, the reputation of the organization, and the legal compliance. Therefore, the risk impact for requirement R1 should be categorized as high or very high, regardless of the likelihood of occurrence. Reference = ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst1, page 2 Risk Based Testing: Approach, Matrix, Process & Examples2, section "Risk Impact Assessment" What is Risk Based Testing: With Best Practices3, section "Risk Impact Analysis"

Topics

#risk-based testing#risk impact#test prioritization#risk assessment