Working together with the test manager during test planning, which of the following activities is NOT expected to be performed by the test analyst? [K2] 1 credit
Options
- AReview the test estimates of the test manager
- BReview the test plan for non-functional testing
- COrganize adequate test resources
- DBeing involved in risk management sessions