Which of the following is a typical work product that the Test Analyst would deliver as part of the test closure activities?
The correct answer is A. A list of all deferred defects. See the full explanation below for the reasoning.
Question
Which of the following is a typical work product that the Test Analyst would deliver as part of the test closure activities?
Options
- AA list of all deferred defects
- BA list of all rejected defect reports
- CA list of all defects found in production and fixed in this release
- DA list of all resolved defects
How the community answered
(36 responses)- A86% (31)
- B8% (3)
- C3% (1)
- D3% (1)