CSSLP · Question #236

CSSLP Question #236: Real Exam Question with Answer & Explanation

Sign in or unlock CSSLP to reveal the answer and full explanation for question #236. The question stem and answer options stay visible for context.

Secure Software Supply Chain

Question

You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of lack of space, casting it is highly dangerous. High technical skill will be required for casting that column. You decide to hire a local expert team for casting that column. Which of the following types of risk response are you following?

Options

  • AAvoidance
  • BAcceptance
  • CMitigation
  • DTransference

Unlock CSSLP to see the answer

You've previewed enough free CSSLP questions. Unlock CSSLP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Transference#Risk Response Strategies#Third-Party Risk Management#Outsourcing