ASQ
CSSBB · Question #74
A process shows the following number of defectives. Each sample size for this process is 85.3 8 2 7 7 6 8 8 9 5 What control chart should be used?
The correct answer is E. np. See the full explanation below for the reasoning.
Control Phase
Question
A process shows the following number of defectives. Each sample size for this process is 85.3 8 2 7 7 6 8 8 9 5 What control chart should be used?
Options
- Ax-bar and R
- Bmedian
- Cindividual and moving range
- Dp
- Enp
- Fc
- Gu
- Hnone of the above
How the community answered
(57 responses)- A7% (4)
- C2% (1)
- D14% (8)
- E74% (42)
- F4% (2)
Topics
#np-chart#attribute control chart#defectives#chart selection