CSSBB · Question #439

Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process and will therefore begin building a(n) ________.

The correct answer is A. FMEA. See the full explanation below for the reasoning.

Analyze Phase

Question

Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process and will therefore begin building a(n) ________.

Options

  • AFMEA
  • BSIPOC
  • CX-Y Diagram
  • DTeam Charter

How the community answered

(38 responses)
  • A
    82% (31)
  • B
    3% (1)
  • C
    5% (2)
  • D
    11% (4)

Topics

#FMEA#risk assessment#failure mode analysis#process risk