Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process and will therefore begin building a(n) ______________.

The correct answer is B. FMEA. See the full explanation below for the reasoning.

Analyze Phase

Question

Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process and will therefore begin building a(n) ______________.

Options

  • ASIPOC
  • BFMEA
  • CBusiness Case
  • DTeam charter