Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process and will therefore begin building a(n) ______________.
The correct answer is B. FMEA. See the full explanation below for the reasoning.
Analyze Phase
Question
Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process and will therefore begin building a(n) ______________.
Options
- ASIPOC
- BFMEA
- CBusiness Case
- DTeam charter
How the community answered
(26 responses)- A4% (1)
- B73% (19)
- C15% (4)
- D8% (2)