ASQ
CSSBB · Question #371
A Belt rearranged the location of the parts inventory for a rework station locating the most often used parts to be within hand reach of the repair person. This rearrangement resulted in quicker…
The correct answer is A. Motion. See the full explanation below for the reasoning.
Improve Phase
Question
A Belt rearranged the location of the parts inventory for a rework station locating the most often used parts to be within hand reach of the repair person. This rearrangement resulted in quicker repair times by eliminating one of seven major elements of waste which is the Waste of __________.
Options
- AMotion
- BConveyance
- CInventory
- DWaiting
How the community answered
(47 responses)- A83% (39)
- B2% (1)
- C11% (5)
- D4% (2)
Topics
#seven wastes#motion waste#lean manufacturing#5S