CSSBB · Question #350
If you can Poka-Yoke a defect out of the process entirely then you do not need use SPC on the characteristic of interest in the defect.
The correct answer is A. True. See the full explanation below for the reasoning.
Control Phase
Question
If you can Poka-Yoke a defect out of the process entirely then you do not need use SPC on the characteristic of interest in the defect.
Options
- ATrue
- BFalse
How the community answered
(37 responses)- A78% (29)
- B22% (8)
Topics
#Poka-Yoke#error proofing#SPC#defect prevention