ASQ
CSSBB · Question #341
The Lean toolbox includes all of the following items except __________.
The correct answer is B. Standard Operating Procedures. See the full explanation below for the reasoning.
Improve Phase
Question
The Lean toolbox includes all of the following items except __________.
Options
- APoke-Yoke
- BStandard Operating Procedures
- CKaizen
- D5S the work area
How the community answered
(18 responses)- A6% (1)
- B72% (13)
- C6% (1)
- D17% (3)
Topics
#Lean tools#Poka-Yoke#Kaizen#5S
Community Discussion
No community discussion yet for this question.