A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt's effort…
The correct answer is B. 2.22. See the full explanation below for the reasoning.
Analyze Phase
Question
A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt’s effort requiring that the average cost of an internal critical raw material component be less than or equal to $3,600 in order to stay within budget. Using a sample of 42 first article components, a Mean of the new product upgrade price of $3,200 and a Standard Deviation of $180 was estimated. Based on the data provided, the Z value for the data assuming a Normal Distribution is?
Options
- A1.11
- B2.22
- C4.30
- D5.42
How the community answered
(28 responses)- A4% (1)
- B79% (22)
- C11% (3)
- D7% (2)
Topics
#Z value calculation#hypothesis testing#normal distribution#one-sample Z-test