CSSBB · Question #287

A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt's effort…

The correct answer is C. Only if the average cost per product upgrade is $4,060, will the purchase manager introduce new. See the full explanation below for the reasoning.

Analyze Phase

Question

A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt’s effort requiring that the average cost of an internal critical raw material component be less than or equal to $4,200 in order to stay within budget. Using a sample of 35 first article components, a Mean of the new product upgrade price of $4,060, and a Standard Deviation of $98 was estimated. Select the answer that best states the Practical Problem.

Options

  • AIf the average cost per component is $4,200 or less, then the purchase manager will introduce the
  • BIf the average cost per component is greater than $4,200, then the purchase manager will
  • COnly if the average cost per product upgrade is $4,060, will the purchase manager introduce new
  • DIf the average cost per new product upgrade is less than $180, then the purchase manager will

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    9% (4)
  • C
    85% (39)
  • D
    2% (1)

Topics

#hypothesis testing#practical problem statement#one-sample test#supply chain