CSSBB · Question #267
Kanban establishes a means of monitoring production, conveyance and delivery information such that efficient flow is established. The method used by Kanban is to require a _________ before anything…
The correct answer is B. Signal. See the full explanation below for the reasoning.
Improve Phase
Question
Kanban establishes a means of monitoring production, conveyance and delivery information such that efficient flow is established. The method used by Kanban is to require a _________ before anything moves.
Options
- ASign-off
- BSignal
- CBell to ring
- DWork order
How the community answered
(45 responses)- A4% (2)
- B71% (32)
- C16% (7)
- D9% (4)
Topics
#Kanban#Lean#pull system#flow management