Upon completion and validation of an improvement to a process a Belt and the Project Team create a Control Plan that contains which of these?
The correct answer is D. All of the above. See the full explanation below for the reasoning.
Control Phase
Question
Upon completion and validation of an improvement to a process a Belt and the Project Team create a Control Plan that contains which of these?
Options
- AStandard operating work description of the process change
- BDescription of the monitoring system in place to assure continued compliance
- CSummary of the targeted critical metrics for process performance measurement
- DAll of the above
How the community answered
(27 responses)- A11% (3)
- B4% (1)
- C4% (1)
- D81% (22)