CSSBB · Question #245

Following the completion of a LSS project the Belt not only creates a Control Plan he also develops a _____________ so those involved in the process know what to do when the critical metrics move…

The correct answer is A. Response Plan. See the full explanation below for the reasoning.

Control Phase

Question

Following the completion of a LSS project the Belt not only creates a Control Plan he also develops a _____________ so those involved in the process know what to do when the critical metrics move out of spec.

Options

  • AResponse Plan
  • BCall List
  • CChain-of-Command
  • DDefect Analysis Plan

How the community answered

(42 responses)
  • A
    81% (34)
  • B
    5% (2)
  • C
    2% (1)
  • D
    12% (5)

Topics

#response plan#control plan#OCAP#project closure