Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for the process?

The correct answer is A. Xbar Chart. See the full explanation below for the reasoning.

Control Phase

Question

Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for the process?

Options

  • AXbar Chart
  • BTime Series Chart
  • CNeither
  • DBoth

How the community answered

(20 responses)
  • A
    85% (17)
  • B
    5% (1)
  • D
    10% (2)

Topics

#OCAP#out-of-control action plan#control chart#special cause