ASQ
CSSBB · Question #238
Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for the process?
The correct answer is A. Xbar Chart. See the full explanation below for the reasoning.
Control Phase
Question
Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for the process?
Options
- AXbar Chart
- BTime Series Chart
- CNeither
- DBoth
How the community answered
(20 responses)- A85% (17)
- B5% (1)
- D10% (2)
Topics
#OCAP#out-of-control action plan#control chart#special cause
Community Discussion