ASQ
CSSBB · Question #231
For a line in an FMEA form a team has established the following: Cost: $82 Severity: 7 Occurrence: 9 Detection: 4 Target date: 7 days What should the risk priority number (RPN) be for this line:
The correct answer is B. 252. See the full explanation below for the reasoning.
Analyze Phase
Question
For a line in an FMEA form a team has established the following:
Cost: $82 Severity: 7 Occurrence: 9 Detection: 4 Target date: 7 days What should the risk priority number (RPN) be for this line:
Options
- A144,648
- B252
- C1764
- D63
- Enone of the above
How the community answered
(42 responses)- A2% (1)
- B71% (30)
- C7% (3)
- D14% (6)
- E5% (2)
Topics
#FMEA#RPN calculation#risk priority number#severity-occurrence-detection
Community Discussion